Construction

Punch List and Inspections

Oct 6, 2026 · 8:35 AM ETRead live from Procore across all 173 active projects
Weekly refresh

1,242 punch items open across 28 jobs; 1,121 are past due, median 194 days

Most past-due items sit with KCL Framing (237), Rite Rug Co. (151), Triple N drywall (133). 380 items were created in the last 30 days. Of 128 inspection lists on these jobs, 0 were performed in the last 30 days and 49 were closed with items still marked not inspected.

7,298
Punch items, all time
1,242
Open
1,121
Past due
194
Median days past due
380
Created last 30 days
0
Inspections last 30 days
49
Lists closed unanswered

By job: open, overdue and how consistently punch is being recorded

Active jobs plus any warranty job with open items. "Unit-located" is the share of items tied to a unit or room in the Procore location tree, which is what makes vendor and warranty reporting possible. Red rows have 50 or more items past due.

JobItemsOpenPast dueOldest (days)New 30dClosed lateUnit-locatedInsp. listsInsp. 30dItems not inspectedConvention flags
QTR - QT Apts II Bldg QWarranty 9753213217530 97%98% 3060%
QTR - QT Apts III Bldg CCourse of Construction 599214214314113 89%92% 6057%
QTR - QT Apts III Bldg GCourse of Construction 23719488214189 65%98% 1080%
QTR - QT Apts III Bldg FCourse of Construction 1081081081720 91% 00
JPK - J67 HB4 270 DickensonWarranty 178888812090 98%0% 1027%items not located to a unit
WGR - Apts I - Bldg BPre-Construction 1046262366 55%91% 1088%
QTR - QT Apts III Bldg BCourse of Construction 5857571322 0%2% 00items not located to a unit
GPK - Grant Pk Apts 5 Bldg AWarranty 13343439480 83%0% 2074%items not located to a unit; items without a vendor
WGR - Apts I - Bldg ABidding 11333337743 94%99% 00
WGR - Apts I - Bldg DBidding 3720132922 100%22% 00items not located to a unit
QTR - QT Apts III Bldg ECourse of Construction 651919920 100%97% 00
JPK - JP9 Apts AmenityWarranty 1312127740 0%0% 100%items not located to a unit
QTR - QT Apts III Community CenterCourse of Construction 1110103120 100%36% 30100%items not located to a unit
GVX - GVX Apts II Bldg ZZCourse of Construction 68966014 95%21% 47077%items not located to a unit; 43 inspection lists closed with unanswered items
QTR - QT Apts III Maintenance BldgCourse of Construction 9881960 100%0% 1077%items not located to a unit
QTR - QT TH&F PB2 2248-2262Warranty 8889010 0% 00items not located to a unit
QTR - QT TH&F HB4 2867 KobukCourse of Construction 115773260 100%99% 8095%
WGR - Apts I - Bldg EBidding 762186 0%14% 1021%items not located to a unit
QTR - QT Apts II Bldg P1-P2Warranty 990555000 93%98% 20100%
QTR - QT Apts III Bldg HCourse of Construction 402442670 93%99% 14012%4 inspection lists closed with unanswered items
QTR - QT Retail Bldg M CoreWarranty 34445800 93%0% 00items not located to a unit
WGR - Apts I - Bldg C - Comm CtrPre-Construction 13633261 85%67% 00
QTR - QT Homes ph4 2374 Quarry TrailsCourse of Construction 32182 100%0% 00items not located to a unit; items without a vendor
QTR - QT Homes ph4 2380 Quarry TrailsCourse of Construction 21182 100%0% 00items not located to a unit
JPK - JP9 AptsWarranty 647117000 89%0% 300%items not located to a unit
GPK - Grant Pk Apts 5 Bldg BWarranty 59115560 93%0% 1049%items not located to a unit
GVX - 810 Apts Bldg ZWarranty 11111170 0% 00items not located to a unit
QTR - QT TH&F HB1 2891 KobukWarranty 11112810 0% 00items not located to a unit
QTR - QT Apts III Bldg DCourse of Construction 648000 93%97% 9051%1 inspection list closed with unanswered items
QTR - QT TH&F HB3 2842 GunnisonCourse of Construction 99000 100%100% 3063%
GVX - GVX Apts II Bldg QCourse of Construction 26000 100%27% 4043%items not located to a unit; 1 inspection list closed with unanswered items
QTR - QT Homes ph2 2853 Katmai Drive (2B)Course of Construction 6000 83%0% 00items not located to a unit; items without a vendor
QTR - QT Homes ph2 2822 Kobuk Drive (8A)Course of Construction 5000 60%0% 00items not located to a unit; items without a vendor
QTR - Qt Homes ph2 2828 Kobuk Drive (10A)Course of Construction 4000 50%0% 00items not located to a unit; items without a vendor
QTR - QT Homes ph2 2792 Kobuk Drive (21)Course of Construction 3000 100%0% 00items not located to a unit; items without a vendor
GVX - GVX Apts II Bldg Q & ZZ Pool & AmenityCourse of Construction 2000 100%100% 00
QTR - QT Homes ph2 2800 Kobuk Drive (4B)Course of Construction 1000 100%0% 00items not located to a unit; items without a vendor
QTR - QT Homes ph2 2806 Kobuk Drive (23)Course of Construction 1000 100%0% 00items not located to a unit; items without a vendor
JPK - J67 HB5 260 DickensonCourse of Construction 0000 100%
QTR - QT Apts III Bldg ACourse of Construction 0000 10100%
QTR - QT TH&F HB5 2855 KobukCourse of Construction 0000 1082%
QTR - QT TH&F HB6 2830 GunnisonCourse of Construction 0000 10100%
QTR - QT Homes ph2 2812 Kobuk Drive (2B)Pre-Construction 3000 67%0% 00items not located to a unit; items without a vendor
QTR - QT Homes ph2 2827 Katmai Drive (7A)Pre-Construction 3000 67%0% 00items not located to a unit; items without a vendor
QTR - Qt Homes ph2 2851 Katmai Drive (2B)Pre-Construction 2000 0%0% 00items not located to a unit; items without a vendor
QTR - QT TH&F PB3 2245-2259 Kings CanyonPre-Construction 0000 2099%
QTR - QT TH&F PB4 2269-2283 Kings CanyonPre-Construction 0000 10100%

Business Partners: who holds the open items and who closes late

All jobs, all time, vendors with 10 or more items. "Closed late" is the share of closed items closed after the due date; "median late" is days past due at close. Red rows have 50 or more items past due today or close late 90 percent of the time. A vendor can appear under more than one Procore company record (Romanoff has three).

Business PartnerItemsJobsOpenPast dueClosed lateMedian days late
KCL Framing8942424323795%78
Rite Rug Co.7462116015192%24
Triple N drywall6341313313399%24
Romanoff Electric, Inc574131029093%19
Thrive Construction50833565293%36
Contract Lumber43414464598%62
Foundation Millwork & Stone4189747496%23
Northern Window & Door3118141496%80
Sims-Lohman, Inc29713433190%20
Holmes Lumber25821735870%5
(no vendor assigned)257420089%61
Precision Wall Systems LLC2449775383%8
Romanoff Electric Residential LLC24317202097%57
TG Plumbing & Mechanical, Inc.2319211091%10
JB Hunt215522100%19
Romanoff Heating & Cooling21217101092%23
RBS Plumbing, LLC2072101099%18
Best Impression Painting LLC1704573596%12
Whirlpool Corporation16876699%19
Granite Direct1479101091%19
James Blinds1379101090%4
GE Appliances1278303094%42
Mike Baumann Plumbing114113391%8
Colonial Heating & Cooling Co., Inc.9554485%13
Whirlpool70100100%14
All Secured Security Services LLC48139890%13
K.E.P. Electric, Inc4854380%10
C & M Services46100100%19
Gutridge4280098%60
Wolfrum Roofing & Exteriors, LLC3867794%192
Surface Tech Inc2869984%6
Elflein Property Solutions2658894%75
S.A. Comunale266171778%18
Interactive Protection Services17211100%25
Hamilton Parker13611100%126
Design Plumbing Inc.11100100%45

Overdue items by job, oldest first

Expand a job for the item, the Business Partner it is assigned to, the location and days past due. Items with no vendor are the superintendent's to assign.

QTR - QT Apts II Bldg Q 321 overdue oldest 753 days
#ItemBusiness PartnerLocationDueDays late
290583 QA WINDOW PUNCHNorthern Window & Door2024-09-13753
295585 QA WINDOW PUNCHNorthern Window & Door2024-09-13753
304587 QA WINDOW PUNCH Northern Window & Door2024-09-13753
297Door DamageNorthern Window & Door2nd Floor Units>2122024-09-14752
291583 QA SURFACE REPAIR Thrive Construction2024-09-19747
307589 QA SURFACE REPAIR Thrive Construction2024-09-19747
420Damaged downspoutWolfrum Roofing & Exteriors, LLC4th Floor Units>4182024-10-20716
448Downspout Wolfrum Roofing & Exteriors, LLC4th Floor Units>4142024-10-21715
455Grout/caulking/flooring Rite Rug Co.4th Floor Units>4122024-10-21715
457Drywall/Caulk/paintTriple N drywall4th Floor Units>4122024-10-21715
461Balcony door/deckingKCL Framing4th Floor Units>4122024-10-24712
464Grout/caulking/flooring Rite Rug Co.4th Floor Units>4192024-10-24712
465Drywall/Caulk/paintTriple N drywall4th Floor Units>4192024-10-24712
467Grout/caulking/flooring Rite Rug Co.4th Floor Units>4102024-10-24712
469Tub slab/countertops/sinkGranite Direct4th Floor Units2024-10-24712
470Balcony door/deckingKCL Framing4th Floor Units>4102024-10-24712
472Drywall/Caulk/paintTriple N drywall4th Floor Units>4172024-10-24712
473Grout/caulking/flooring Rite Rug Co.4th Floor Units>4172024-10-24712
475Drywall/Caulk/paintTriple N drywall4th Floor Units>4082024-10-24712
477Grout/caulking/flooring Rite Rug Co.4th Floor Units>4082024-10-24712
479Balcony door/deckingKCL Framing4th Floor Units>4082024-10-24712
482Drywall/Caulk/paintTriple N drywall4th Floor Units>4132024-10-24712
483Balcony door/deckingKCL Framing4th Floor Units>4132024-10-24712
486Balcony door/deckingKCL Framing4th Floor Units>4112024-10-24712
489Grout/caulking/flooring Rite Rug Co.4th Floor Units>4092024-10-24712
491Grout/caulking/flooring Rite Rug Co.4th Floor Units>4062024-10-24712
495Balcony door/deckingKCL Framing4th Floor Units>4062024-10-24712
506Grout/caulking/flooring Rite Rug Co.4th Floor Units>4042024-10-24712
513Balcony door/deckingKCL Framing4th Floor Units>4032024-10-24712
518Balcony door/deckingKCL Framing4th Floor Units>4022024-10-24712
523Drywall/Caulk/paintTriple N drywall4th Floor Units>4222024-10-25711
524Balcony door/deckingKCL Framing4th Floor Units>4222024-10-25711
528Drywall/Caulk/paintTriple N drywall3rd Floor Units>3012024-10-25711
532Grout/caulking/flooring Rite Rug Co.3rd Floor Units>3022024-10-25711
533Drywall/Caulk/paintTriple N drywall3rd Floor Units>3022024-10-25711
535Electrical Romanoff Electric Residential LLC, Romanoff Electric, Inc3rd Floor Units2024-10-25711
536Drywall/Caulk/paintTriple N drywall3rd Floor Units>3032024-10-25711
539Grout/caulking/flooring Rite Rug Co.3rd Floor Units>3042024-10-25711
542Grout/caulking/flooring Rite Rug Co.3rd Floor Units>3052024-10-25711
543Drywall/Caulk/paintTriple N drywall3rd Floor Units>3052024-10-25711
Showing the 40 oldest of 321 overdue items.
QTR - QT Apts III Bldg C 214 overdue oldest 314 days
#ItemBusiness PartnerLocationDueDays late
2101 KCL Frame punchKCL FramingBUILDING C>OVERALL - FIRST FLOOR PLAN>UNIT 101 5B O.C.2025-11-26314
3102 KCL Frame punchKCL FramingBUILDING C>OVERALL - FIRST FLOOR PLAN>UNIT 102 5B O.C.2025-11-26314
4103 KCL Frame punchKCL FramingBUILDING C>OVERALL - FIRST FLOOR PLAN>UNIT 103 13B2025-11-26314
5104 KCL Frame punchKCL FramingBUILDING C>OVERALL - FIRST FLOOR PLAN>UNIT 104 13B2025-11-26314
6105 KCL Frame punchKCL FramingBUILDING C>OVERALL - FIRST FLOOR PLAN>UNIT 105 4B2025-11-26314
7106 KCL Frame punchKCL FramingBUILDING C>OVERALL - FIRST FLOOR PLAN>UNIT 106 4B2025-11-26314
8107 KCL Frame punchKCL FramingBUILDING C>OVERALL - FIRST FLOOR PLAN>UNIT 107 4B2025-11-26314
9108 KCL Frame punchKCL FramingBUILDING C>OVERALL - FIRST FLOOR PLAN>UNIT 108 4B2025-11-28312
10109 KCL Frame punchKCL Framing2025-11-28312
11110 KCL Frame punchKCL FramingBUILDING C>OVERALL - FIRST FLOOR PLAN>UNIT 110 3B2025-12-05305
12111 KCL Frame punchKCL FramingBUILDING C>OVERALL - FIRST FLOOR PLAN>MECH. 1112025-12-05305
13112 KCL Frame punchKCL FramingBUILDING C>OVERALL - FIRST FLOOR PLAN>UNIT 112 3B2025-12-05305
15113 KCL Frame punchKCL FramingBUILDING C>OVERALL - FIRST FLOOR PLAN>UNIT 113 5B2025-12-05305
16115 KCL Frame punchKCL FramingBUILDING C>OVERALL - FIRST FLOOR PLAN>UNIT 115 4B2025-12-09301
17116 KCL Frame punchKCL FramingBUILDING C>OVERALL - FIRST FLOOR PLAN>UNIT 116 4B2025-12-09301
18117 KCL Frame punchKCL FramingBUILDING C>OVERALL - FIRST FLOOR PLAN>UNIT 117 4B2025-12-11299
19118 KCL Frame punchKCL FramingBUILDING C>OVERALL - FIRST FLOOR PLAN>UNIT 118 3B2025-12-11299
20119 KCL Frame punchKCL FramingBUILDING C>OVERALL - FIRST FLOOR PLAN>UNIT 119 13B2025-12-22288
21120 KCL Frame punchKCL FramingBUILDING C>OVERALL - FIRST FLOOR PLAN>UNIT 120 7B2025-12-22288
22121 KCL Frame punchKCL FramingBUILDING C>OVERALL - FIRST FLOOR PLAN>UNIT 121 5B O.C.2025-12-23287
23Add 1 jack to both sides of east bedroom window opening. H3 headers need 4 jacks each endKCL FramingBUILDING C>OVERALL - FIRST FLOOR PLAN>UNIT 119 13B2026-01-09270
24Remove floor trusses above fire suppression chase. Add girder trussKCL FramingBUILDING C>OVERALL - FIRST FLOOR PLAN>UNIT 122 5B O.C.2026-01-12267
25Straighten/level wall and openings on porch/living room wall and add jack stud to each end. Lower corner window to correct height. KCL FramingBUILDING C>OVERALL - FIRST FLOOR PLAN>UNIT 102 5B O.C.2026-01-12267
26Add hangers and pack studs to girder truss above chase in bathroomKCL FramingBUILDING C>OVERALL - FIRST FLOOR PLAN>UNIT 101 5B O.C.2026-01-12267
27Close in F type windows in living and bedrooms to correct height opening. Should be 78ro, not 88"KCL FramingBUILDING C>OVERALL - FIRST FLOOR PLAN>UNIT 103 13B2026-01-12267
28Add 2 jacks under each side of header per schedule KCL FramingBUILDING C>OVERALL - FIRST FLOOR PLAN>UNIT 118 3B2026-01-12267
29Install LVL header on bedroom window per scheduleKCL FramingBUILDING C>OVERALL - FIRST FLOOR PLAN>UNIT 115 4B2026-01-12267
30Install LVL header above bedroom windowKCL FramingBUILDING C>OVERALL - FIRST FLOOR PLAN>UNIT 117 4B2026-01-12267
32202 Frame punch KCLKCL Framing2026-03-02218
33203 Frame punch KCLKCL Framing2026-03-02218
38208 Frame punch KCLKCL Framing2026-03-02218
41210 Frame punch KCLKCL Framing2026-03-02218
44214 Frame punch KCLKCL Framing2026-03-03217
53Wall, window, and door opening not levelKCL FramingBUILDING C>OVERALL - FIRST FLOOR PLAN>UNIT 102 5B O.C.2026-03-05215
56303 Frame punch KCLKCL Framing2026-03-06214
102422 Frame punch KCLKCL FramingBUILDING C>OVERALL - FOURTH FLOOR PLAN>UNIT 422 5B O.C.2026-03-17203
128102 Romanoff Box PunchRomanoff Electric, IncBUILDING C>OVERALL - FIRST FLOOR PLAN>UNIT 102 5B O.C.2026-05-04155
129103 Romanoff Box PunchRomanoff Electric, IncBUILDING C>OVERALL - FIRST FLOOR PLAN>UNIT 103 13B2026-05-04155
130104 Romanoff Box PunchRomanoff Electric, IncBUILDING C>OVERALL - FIRST FLOOR PLAN>UNIT 104 13B2026-05-04155
131105 Romanoff Box PunchRomanoff Electric, IncBUILDING C>OVERALL - FIRST FLOOR PLAN>UNIT 105 4B2026-05-04155
Showing the 40 oldest of 214 overdue items.
QTR - QT Apts III Bldg G 88 overdue oldest 214 days
#ItemBusiness PartnerLocationDueDays late
1Kitchen island short. Should be 87” inside clearanceKCL FramingBUILDING G>OVERALL - FIRST FLOOR PLAN>UNIT 106 8B2026-03-06214
3101 KCL Frame PunchKCL FramingBUILDING G>OVERALL - FIRST FLOOR PLAN>UNIT 101 5B O.C.2026-03-17203
4102 KCL Frame PunchKCL FramingBUILDING G>OVERALL - FIRST FLOOR PLAN>UNIT 102 5B O.C.2026-03-17203
5103 KCL Frame PunchKCL FramingBUILDING G>OVERALL - FIRST FLOOR PLAN>UNIT 103 8B2026-03-17203
6104 KCL Frame PunchKCL Framing2026-03-17203
7105 KCL Frame PunchKCL FramingBUILDING G>OVERALL - FIRST FLOOR PLAN>UNIT 105 3B2026-03-17203
8106 KCL Frame PunchKCL FramingBUILDING G>OVERALL - FIRST FLOOR PLAN>UNIT 106 8B2026-03-17203
9107 KCL Frame PunchKCL FramingBUILDING G>OVERALL - FIRST FLOOR PLAN>UNIT 107 8B2026-03-17203
10108 KCL Frame PunchKCL FramingBUILDING G>OVERALL - FIRST FLOOR PLAN>UNIT 108 4B2026-03-17203
11109 KCL Frame PunchKCL FramingBUILDING G>OVERALL - FIRST FLOOR PLAN>UNIT 109 13B2026-03-17203
12110 KCL Frame PunchKCL FramingBUILDING G>OVERALL - FIRST FLOOR PLAN>UNIT 110 7A2026-03-17203
13111 KCL Frame PunchKCL FramingBUILDING G>OVERALL - FIRST FLOOR PLAN>UNIT 111 5B O.C.2026-03-17203
14112 KCL Frame PunchKCL FramingBUILDING G>OVERALL - FIRST FLOOR PLAN>UNIT 112 5B O.C.2026-03-17203
15201 KCL Frame PunchKCL FramingBUILDING G>OVERALL - SECOND FLOOR PLAN>UNIT 201 5 O.C.2026-03-19201
16202 KCL Frame PunchKCL FramingBUILDING G>OVERALL - SECOND FLOOR PLAN>UNIT 202 5 O.C.2026-03-19201
17203 KCL Frame PunchKCL FramingBUILDING G>OVERALL - SECOND FLOOR PLAN>UNIT 203 82026-03-19201
18204 KCL Frame PunchKCL FramingBUILDING G>OVERALL - SECOND FLOOR PLAN>UNIT 204 132026-03-19201
19205 KCL Frame PunchKCL FramingBUILDING G>OVERALL - SECOND FLOOR PLAN>UNIT 205 32026-03-19201
20206 KCL Frame PunchKCL FramingBUILDING G>OVERALL - SECOND FLOOR PLAN>UNIT 206 82026-03-19201
21207 KCL Frame PunchKCL FramingBUILDING G>OVERALL - SECOND FLOOR PLAN>UNIT 207 82026-03-19201
22208 KCL Frame PunchKCL FramingBUILDING G>OVERALL - SECOND FLOOR PLAN>UNIT 208 42026-03-19201
23209 KCL Frame PunchKCL FramingBUILDING G>OVERALL - SECOND FLOOR PLAN>UNIT 209 132026-03-19201
24210 KCL Frame PunchKCL FramingBUILDING G>OVERALL - SECOND FLOOR PLAN>UNIT 210 72026-03-19201
25211 KCL Frame PunchKCL FramingBUILDING G>OVERALL - SECOND FLOOR PLAN>UNIT 211 5 O.C.2026-03-19201
26212 KCL Frame PunchKCL FramingBUILDING G>OVERALL - SECOND FLOOR PLAN>UNIT 212 5 O.C.2026-03-19201
27301 KCL Frame PunchKCL FramingBUILDING G>OVERALL - THIRD FLOOR PLAN>UNIT 301 5 O.C.2026-03-26194
28302 KCL Frame PunchKCL FramingBUILDING G>OVERALL - THIRD FLOOR PLAN>UNIT 302 5 O.C.2026-03-26194
29303 KCL Frame PunchKCL FramingBUILDING G>OVERALL - THIRD FLOOR PLAN>UNIT 303 82026-03-26194
30304 KCL Frame PunchKCL FramingBUILDING G>OVERALL - THIRD FLOOR PLAN>UNIT 304 132026-03-26194
31305 KCL Frame PunchKCL FramingBUILDING G>OVERALL - THIRD FLOOR PLAN>UNIT 305 32026-03-26194
32306 KCL Frame PunchKCL FramingBUILDING G>OVERALL - THIRD FLOOR PLAN>UNIT 306 82026-03-26194
33307 KCL Frame PunchKCL FramingBUILDING G>OVERALL - THIRD FLOOR PLAN>UNIT 307 82026-03-26194
34308 KCL Frame PunchKCL FramingBUILDING G>OVERALL - THIRD FLOOR PLAN>UNIT 308 42026-03-26194
35309 KCL Frame PunchKCL FramingBUILDING G>OVERALL - THIRD FLOOR PLAN>UNIT 309 132026-03-26194
36310 KCL Frame PunchKCL FramingBUILDING G>OVERALL - THIRD FLOOR PLAN>UNIT 310 72026-03-26194
37311 KCL Frame PunchKCL FramingBUILDING G>OVERALL - THIRD FLOOR PLAN>UNIT 311 5 O.C.2026-03-26194
40Holmes Window PunchHolmes Lumber2026-04-23166
41Romanoff Third Floor Box PunchRomanoff Electric, Inc2026-05-15144
42Romanoff Second Floor Box PunchRomanoff Electric, Inc2026-05-15144
43Romanoff Third Floor Lighting PunchRomanoff Electric, IncBUILDING G>OVERALL - THIRD FLOOR PLAN2026-05-15144
Showing the 40 oldest of 88 overdue items.
QTR - QT Apts III Bldg F 108 overdue oldest 172 days
#ItemBusiness PartnerLocationDueDays late
1Window rough opening needs fixedKCL FramingBUILDING F>OVERALL - SECOND FLOOR PLAN>UNIT 209 5B2026-04-17172
2Window rough opening needs fixedKCL FramingBUILDING F>OVERALL - SECOND FLOOR PLAN>UNIT 207 4B2026-04-17172
3Window rough opening needs fixedKCL FramingBUILDING F>OVERALL - SECOND FLOOR PLAN>UNIT 208 4B2026-04-17172
4Window rough opening needs fixedKCL FramingBUILDING F>OVERALL - SECOND FLOOR PLAN>UNIT 205 4B2026-04-17172
5Truss hanging down too lowKCL FramingBUILDING F>OVERALL - FIRST FLOOR PLAN>UNIT 122 5B O.C.2026-04-20169
6Missing chase wallKCL FramingBUILDING F>OVERALL - FIRST FLOOR PLAN>UNIT 122 5B O.C.2026-04-20169
7Floor truss needs moved for shower drain aboveKCL FramingBUILDING F>OVERALL - FIRST FLOOR PLAN>UNIT 101 5B O.C.2026-04-20169
8Move truss in laundry areaKCL FramingBUILDING F>OVERALL - FIRST FLOOR PLAN>UNIT 102 5B O.C.2026-04-24165
9Move truss for toilet drain penitrtionKCL FramingBUILDING F>OVERALL - FIRST FLOOR PLAN>UNIT 118 3B2026-04-24165
10101 KCL Frame PunchKCL FramingBUILDING F>OVERALL - FIRST FLOOR PLAN>UNIT 101 5B O.C.2026-05-22137
11102 KCL Frame PunchKCL FramingBUILDING F>OVERALL - FIRST FLOOR PLAN>UNIT 102 5B O.C.2026-05-22137
12103 KCL Frame PunchKCL FramingBUILDING F>OVERALL - FIRST FLOOR PLAN>UNIT 103 13B2026-05-22137
13104 KCL Frame PunchKCL FramingBUILDING F>OVERALL - FIRST FLOOR PLAN>UNIT 104 13B2026-05-22137
14105 KCL Frame PunchKCL FramingBUILDING F>OVERALL - FIRST FLOOR PLAN>UNIT 105 4B2026-05-22137
15106 KCL Frame PunchKCL FramingBUILDING F>OVERALL - FIRST FLOOR PLAN>UNIT 106 4B2026-05-22137
16107 KCL Frame PunchKCL FramingBUILDING F>OVERALL - FIRST FLOOR PLAN>UNIT 107 4B2026-05-22137
17108 KCL Frame PunchKCL FramingBUILDING F>OVERALL - FIRST FLOOR PLAN>UNIT 108 4B2026-05-22137
18109 KCL Frame PunchKCL FramingBUILDING F>OVERALL - FIRST FLOOR PLAN>UNIT 109 5B TUB OPTION2026-05-22137
19110 KCL Frame PunchKCL FramingBUILDING F>OVERALL - FIRST FLOOR PLAN>UNIT 110 3B2026-05-22137
20112 KCL Frame PunchKCL FramingBUILDING F>OVERALL - FIRST FLOOR PLAN>UNIT 112 3B2026-05-22137
21114 KCL Frame PunchKCL FramingBUILDING F>OVERALL - FIRST FLOOR PLAN>UNIT 114 4B2026-05-22137
22115 KCL Frame PunchKCL FramingBUILDING F>OVERALL - FIRST FLOOR PLAN>UNIT 115 4B TUB OPTION2026-05-22137
23116 KCL Frame PunchKCL FramingBUILDING F>OVERALL - FIRST FLOOR PLAN>UNIT 116 4B2026-05-22137
24117 KCL Frame PunchKCL FramingBUILDING F>OVERALL - FIRST FLOOR PLAN>UNIT 117 4B2026-05-22137
25118 KCL Frame PunchKCL FramingBUILDING F>OVERALL - FIRST FLOOR PLAN>UNIT 118 3B2026-05-22137
26119 KCL Frame PunchKCL FramingBUILDING F>OVERALL - FIRST FLOOR PLAN>UNIT 119 13B2026-05-22137
27122 KCL Frame PunchKCL FramingBUILDING F>OVERALL - FIRST FLOOR PLAN>UNIT 122 5B O.C.2026-05-22137
28201 KCL Frame PunchKCL FramingBUILDING F>OVERALL - SECOND FLOOR PLAN>UNIT 201 5B O.C.2026-05-25134
29202 KCL Frame PunchKCL FramingBUILDING F>OVERALL - SECOND FLOOR PLAN>UNIT 202 5B O.C.2026-05-25134
30203 KCL Frame PunchKCL FramingBUILDING F>OVERALL - SECOND FLOOR PLAN>UNIT 203 13B2026-05-25134
31204 KCL Frame PunchKCL FramingBUILDING F>OVERALL - SECOND FLOOR PLAN>UNIT 204 13B2026-05-25134
32205 KCL Frame PunchKCL FramingBUILDING F>OVERALL - SECOND FLOOR PLAN>UNIT 205 4B2026-05-25134
33206 KCL Frame PunchKCL FramingBUILDING F>OVERALL - SECOND FLOOR PLAN>UNIT 206 4B2026-05-25134
34207 KCL Frame PunchKCL FramingBUILDING F>OVERALL - SECOND FLOOR PLAN>UNIT 207 4B2026-05-25134
35208 KCL Frame PunchKCL FramingBUILDING F>OVERALL - SECOND FLOOR PLAN>UNIT 208 4B2026-05-25134
36209 KCL Frame PunchKCL FramingBUILDING F>OVERALL - SECOND FLOOR PLAN>UNIT 209 5B2026-05-25134
37210 KCL Frame PunchKCL FramingBUILDING F>OVERALL - SECOND FLOOR PLAN>UNIT 210 3B2026-05-25134
38211 KCL Frame PunchKCL FramingBUILDING F>OVERALL - SECOND FLOOR PLAN>UNIT 211 3B2026-05-25134
39212 KCL Frame PunchKCL FramingBUILDING F>OVERALL - SECOND FLOOR PLAN>UNIT 212 3B2026-05-26133
40213 KCL Frame PunchKCL FramingBUILDING F>OVERALL - SECOND FLOOR PLAN>UNIT 213 5B2026-05-26133
Showing the 40 oldest of 108 overdue items.
JPK - J67 HB4 270 Dickenson 88 overdue oldest 1209 days
#ItemBusiness PartnerLocationDueDays late
105202 - Remove 2 x 4 from top of laundry roomContract Lumber2023-06-151209
138Whole Building - Add blocking for laundry cabinetsContract Lumber2023-06-151209
106203 - Remove 2 x 4 from kitchen wallContract Lumber2023-06-151209
137Whole Building - Improve temp railingsContract Lumber2023-06-151209
102201 - Crowned stud in the bathtub stallContract Lumber2023-06-151209
104202 - Tub corners are not squareContract Lumber2023-06-151209
103202 - Bathtub opening to be 5 foot wide on the moneyContract Lumber2023-06-151209
107203 - Crown stud in the bathtub stallContract Lumber2023-06-151209
109203 - Need blocking for bathroom sinkContract Lumber2023-06-151209
110204 - Crown stud in the bathtub stallContract Lumber2023-06-151209
111204 - Need one more piece of blockingContract Lumber2023-06-151209
112204 - Need closet door next to the entry doorContract Lumber2023-06-151209
101201 - Blocking for kitchen wallContract Lumber2023-06-151209
113204 - Blocking for the kitchen sinkContract Lumber2023-06-151209
108203 - Need blocking for bathroom in hallwayContract Lumber2023-06-151209
143Fourth floor corridor need hangers, hangers need nailsContract Lumber2023-06-151209
142Third floor north stair tower bolts need tightened downContract Lumber2023-06-151209
141Third floor south stair tower need bolts fastened down to the ledger, tighten bolts on opposite side of wall Contract Lumber2023-06-151209
140Second floor need hangerContract Lumber2023-06-151209
139Second floor north stair tower needs bolts fastened to ledgerContract Lumber2023-06-151209
136Need platforms in elevator shaftContract Lumber2023-06-151209
161Unit 401. Dent in fridge door.  Unit 401.GE Appliances2024-10-03733
164Unit 401. Finish base left of water heater and laundry room. Rite Rug Co.2024-10-03733
167Unit 401. Pocket door guides missing laundry room. Rite Rug Co.2024-10-03733
168Unit 401. Repair scratches to exterior of sliding door frames. Surface Tech Inc2024-10-03733
169Unit 401. Missing doorstop on hall bath door. Rite Rug Co.2024-10-03733
171 Unit 401. Bedroom number one missing ball catch at top of closet door. Rite Rug Co.2024-10-03733
172Unit 401. Guest bathroom mirror is chipped. Needs replaced. Rite Rug Co.2024-10-03733
177Unit 404. Repair weatherstrip at bottom of sliding door.  Unit 404.Rite Rug Co.2024-10-03733
178Unit 404. Fill all nail holes in cabinet trim white. Paint edges of toe kick in kitchen white.  Unit 404.Rite Rug Co.2024-10-03733
179Unit 404. Adjust all cabinet faces. Rite Rug Co.2024-10-03733
180Unit 404. Range hood - gap at bottom of shroud. Metal buckled at top of hood assembly. Remove all plastic. GE Appliances2024-10-03733
181Unit 404. Finish install of microwave drawer. Need wood fillers around face. Rite Rug Co.2024-10-03733
182Unit 404. Repair and reinstall pocket door hardware in the laundry room. Rite Rug Co.2024-10-03733
183Unit 404. Pocket door two laundry room is rubbing. Either adjust hardware or replace slab.  is also missing second door guide at bottom. Rite Rug Co.2024-10-03733
186Unit 404. Touch up all scratches to exterior of sliding door. Surface Tech Inc2024-10-03733
188 Unit 404. Repair wall around toilet supply line. Hall bath. Triple N drywall2024-10-03733
189Unit 404. Rehang hall vanity mirror to be centered above cabinet. Rite Rug Co.2024-10-03733
191Unit 404. Owner’s bath exhaust fan not turning on. Romanoff Electric Residential LLC, Romanoff Heating & Cooling2024-10-03733
192Unit 402. Peep hole missing from front door. Thrive Construction2024-10-03733
Showing the 40 oldest of 88 overdue items.
WGR - Apts I - Bldg B 62 overdue oldest 36 days
#ItemBusiness PartnerLocationDueDays late
11Bath closet drywall neededPrecision Wall Systems LLC1st Floor2026-08-3136
20Float ceiling in 303 Precision Wall Systems LLC3rd Floor>3032026-08-3136
21Brick not sitting on brick ledge. Install lentils/go down to ledge.Carlisle Masonry1st Floor2026-08-3136
26Missing light in kitchenPrecision Wall Systems LLC3rd Floor>3012026-08-3136
28Missing lightPrecision Wall Systems LLC3rd Floor>3062026-08-3136
33108 Drywall Precision Wall Systems LLC1st Floor>1082026-08-3136
35203 Drywall Precision Wall Systems LLC1st Floor>1082026-08-3136
36208 Missing lightPrecision Wall Systems LLC2nd Floor>2082026-08-3136
38203 Drywall Precision Wall Systems LLC2nd Floor>2032026-08-3136
41Patch owner closer at baseboard unit 311Precision Wall Systems LLC3rd Floor>3112026-08-3136
42Complete hardware install 313Foundation Millwork & Stone3rd Floor>3132026-08-3136
43Complete cabinet/hardware install 314Foundation Millwork & Stone3rd Floor>3142026-08-3136
44Complete the cab/hardware install in unit 307Foundation Millwork & Stone3rd Floor>3072026-08-3136
46Complete cabinet/hardware install 304Foundation Millwork & Stone3rd Floor>3042026-08-3136
47Complete cab/hardware install 204Foundation Millwork & Stone2nd Floor>2042026-08-3136
51Finish hardware install 301Foundation Millwork & Stone3rd Floor>3012026-08-3136
52Finish hardware install 302Foundation Millwork & Stone3rd Floor>3022026-08-3136
53Finish hardware install 303Foundation Millwork & Stone3rd Floor>3032026-08-3136
54Finish hardware install 305Foundation Millwork & Stone3rd Floor>3052026-08-3136
55Finish hardware install 306Foundation Millwork & Stone3rd Floor>3062026-08-3136
57Finish hardware install 309Foundation Millwork & Stone3rd Floor>3092026-08-3136
59Wrong color too 306 kitchenFoundation Millwork & Stone3rd Floor2026-08-3136
60112 Cabinets Foundation Millwork & Stone1st Floor>1122026-08-3136
61110 Cabinets Foundation Millwork & Stone1st Floor>1102026-08-3136
62111 Cabinets Foundation Millwork & Stone1st Floor>1112026-08-3136
63102 Cabinets Foundation Millwork & Stone1st Floor>1022026-08-3136
64204 Cabinets Foundation Millwork & Stone2nd Floor>2042026-08-3136
65104 Cabinets Foundation Millwork & Stone1st Floor>1042026-08-3136
66211 Cabinets Foundation Millwork & Stone2nd Floor>2112026-08-3136
67213 Cabinets Foundation Millwork & Stone2nd Floor>2132026-08-3136
68103 Cabinets Foundation Millwork & Stone1st Floor>1032026-08-3136
70214 Countertops Foundation Millwork & Stone2nd Floor>2142026-08-3136
71311 Countertops Foundation Millwork & Stone3rd Floor>3112026-08-3136
72310 Countertops Foundation Millwork & Stone3rd Floor>3102026-08-3136
73307 Countertops Foundation Millwork & Stone3rd Floor>3072026-08-3136
74306 Countertops Foundation Millwork & Stone3rd Floor>3062026-08-3136
75305 Countertops Foundation Millwork & Stone3rd Floor>3062026-08-3136
76305 cabinetsFoundation Millwork & Stone3rd Floor>3052026-08-3136
77304 Cabinets Foundation Millwork & Stone3rd Floor>3042026-08-3136
78304 Countertops Foundation Millwork & Stone3rd Floor>3042026-08-3136
Showing the 40 oldest of 62 overdue items.
QTR - QT Apts III Bldg B 57 overdue oldest 13 days
#ItemBusiness PartnerLocationDueDays late
1Unit 201 patio has no zip tape on outside corners or below the deckingKCL Framing2026-09-2313
2No zip tape on outside corners or below decking on patioKCL Framing2026-09-2313
4X19 Stack Units Bedroom Window in Wrong LocationKCL FramingBuilding B>OVERALL - FIRST FLOOR PLAN>UNIT 119 13B2026-09-2313
5Missing stud corner of plumbing wall in bathroom 421KCL Framing2026-09-2313
6#422 missing stud on plumbing wallKCL Framing2026-09-2313
7117 missing bedroom windowHolmes Lumber2026-09-2313
8119 Both (108”x78”) windows sagging in the middle by 1/2” -Broken upper sash in bedroomKCL Framing2026-09-2313
11316 Replace king stud that is nearly attachedKCL Framing2026-09-2313
12315 Replace broken stud in on plumbing wall of tub. It’s cracked where the glass goesKCL Framing, Thrive Construction2026-09-2313
16305 Shower not square Needs to come out 1/2” in the corner KCL Framing, Thrive Construction2026-09-2313
20302 Add stud in master shower plumbing wall @ 36” off back wall for blockingKCL Framing, Thrive Construction2026-09-2313
21222 replace king stud cut out by electrician KCL Framing, Thrive Construction2026-09-2313
23220 Stud in back of tub area not planeWallace Construction2026-09-2313
29213 King stud cutWallace Construction2026-09-2313
30212 Header sags 5/8”Wallace Construction2026-09-2313
332 upper sashes in 2nd floor lobby crackedHolmes Lumber2026-09-2313
34209 Add stud in tub plumbing wall at 31 1/4 Blocking for glass doorThrive Construction2026-09-2313
38208 Cracked top sash in B.R.Holmes Lumber2026-09-2313
40207 Add stud in tub chase wall at 31 1/4” for blockingThrive Construction2026-09-2313
42204 Tub needs blocking at 31 1/4” on plumbing wallThrive Construction2026-09-2313
43102 Broken bottom sash in B.R.Holmes Lumber2026-09-2313
44102 Add nailer at.corner of knee wallThrive Construction2026-09-2313
46104Thrive Construction2026-09-2313
47104 Shower needs stud at 36” Thrive Construction2026-09-2313
48104 Shower needs stud at 36” Thrive Construction2026-09-2313
49104 Broken upper sash needs replaced in B.R.Holmes Lumber2026-09-2313
50106 Bottom plate off 1/2”Thrive Construction2026-09-2313
51105 Header not flush with bottom plateThrive Construction2026-09-2313
52109 Replace missing king studs at unit entryThrive Construction2026-09-2313
53101 Replace missing king studsThrive Construction2026-09-2313
54102 Thrive Construction2026-09-2313
55102 Replace missing king studsThrive Construction2026-09-2313
56109 Header hangs 1/2” over bottom plateThrive Construction2026-09-2313
57110 Missing studs at 36” on chase wall for blockingThrive Construction2026-09-2313
58110 HEADER & bottom plate out 1/2”Thrive Construction2026-09-2313
59113 Add stud at 36” for blockingThrive Construction2026-09-2313
60113 Add 2 King studs that were cut outThrive Construction2026-09-2313
61113 Header sticks out 1/2” over from bottom plateThrive Construction2026-09-2313
62113 Bottom plate of header sags 1/2”Thrive Construction2026-09-2313
63115 Tub area needs studs at 31 1/4” on both sides for blockingThrive Construction2026-09-2313
Showing the 40 oldest of 57 overdue items.
GPK - Grant Pk Apts 5 Bldg A 43 overdue oldest 948 days
#ItemBusiness PartnerLocationDueDays late
101201A Paint/DrywallTriple N drywall2024-03-02948
103202A Closet ShelvingRite Rug Co.2024-03-02948
26201A Punch S.A.CS.A. Comunale2024-03-22928
45302A Punch S.A.CS.A. Comunale2024-03-23927
28202A Punch S.A.CS.A. Comunale2024-03-26924
32203A Punch S.A.CS.A. Comunale2024-03-26924
40204A Punch S.A.CS.A. Comunale2024-03-26924
52304A Punch S.A.CS.A. Comunale2024-03-26924
43301A Punch S.A.CS.A. Comunale2024-03-27923
50303A Punch S.A.CS.A. Comunale2024-03-27923
56305A Punch S.A.CS.A. Comunale2024-03-27923
61306A Punch S.A.CS.A. Comunale2024-03-29921
69206A Punch PlumbingMike Baumann Plumbing2024-03-29921
85107A Punch S.A.C.S.A. Comunale2024-03-29921
87108A Punch PlumbingMike Baumann Plumbing2024-03-29921
89108A Punch S.A.C.S.A. Comunale2024-03-29921
105203A Closet ShelvingRite Rug Co.2024-03-30920
112302A Paint/DrywallTriple N drywall2024-03-31919
95101A Paint/DrywallTriple N drywall2024-04-02917
97102A ShelvingRite Rug Co.2024-04-02917
98102A Paint/DrywallTriple N drywall2024-04-02917
99103A Paint/DrywallTriple N drywall2024-04-02917
100104A Paint/DrywallTriple N drywall2024-04-02917
104202A Paint/DrywallTriple N drywall2024-04-02917
106203A Paint/DrywallTriple N drywall2024-04-02917
107204A Paint/DrywallTriple N drywall2024-04-02917
109301A Paint/DrywallTriple N drywall2024-04-02917
110302A S.A.CS.A. Comunale2024-04-02917
113303A Paint/DrywallTriple N drywall2024-04-02917
115304A Paint/DrywallTriple N drywall2024-04-02917
116105A Paint/DrywallTriple N drywall2024-04-02917
117106A Paint/DrywallTriple N drywall2024-04-02917
120107A Paint/DrywallTriple N drywall2024-04-02917
121108A Paint/DrywallTriple N drywall2024-04-02917
122205A Paint/DrywallTriple N drywall2024-04-02917
124206A Paint/DrywallTriple N drywall2024-04-02917
126207A ShelvingRite Rug Co.2024-04-02917
127207A Paint/DrywallTriple N drywall2024-04-02917
129305A Paint/DrywallTriple N drywall2024-04-02917
130306A Paint/DrywallTriple N drywall2024-04-02917
Showing the 40 oldest of 43 overdue items.
WGR - Apts I - Bldg A 33 overdue oldest 774 days
#ItemBusiness PartnerLocationDueDays late
93102 countertop Foundation Millwork & Stone1st floor>1022024-08-23774
33111 Broken windowHolmes Lumber1st floor>1112026-07-2375
34210 broken windowsHolmes Lumber2nd Floor>2102026-07-2474
42101 Cabinets Foundation Millwork & Stone1st floor>1012026-08-0364
43101 Drywall Precision Wall Systems LLC1st floor>1012026-08-0364
67111 CabinetsFoundation Millwork & Stone1st floor>1112026-08-0562
68109 Cabinets Foundation Millwork & Stone1st floor>1092026-08-0562
69107 Cabinets Foundation Millwork & Stone1st floor>1072026-08-0562
66302 countertops Foundation Millwork & Stone3rd Floor>3022026-08-0760
81213 countertops Foundation Millwork & Stone2nd Floor>2132026-08-1849
85207 cabinets Foundation Millwork & Stone2nd Floor>2072026-08-1849
87203 cabinets Foundation Millwork & Stone2nd Floor>2032026-08-1849
90201 Cabinets Foundation Millwork & Stone2nd Floor>2012026-08-1849
91204 Cabinets Foundation Millwork & Stone2nd Floor>2042026-08-1849
101208 Cabinets Foundation Millwork & Stone2nd Floor>2082026-08-2047
102210 countertops Foundation Millwork & Stone2nd Floor>2082026-08-2047
103209 Countertops Foundation Millwork & Stone2nd Floor>2092026-08-2047
104211 Countertops Foundation Millwork & Stone2nd Floor>2112026-08-2047
105213 Countertops Foundation Millwork & Stone2nd Floor>2142026-08-2047
106213 Countertops Foundation Millwork & Stone2nd Floor>2132026-08-2047
107212 Countertops Foundation Millwork & Stone2nd Floor>2122026-08-2047
92101 countertops Foundation Millwork & Stone1st floor>1012026-08-2146
94103 countertops Foundation Millwork & Stone1st floor>1032026-08-2146
95104 countertops Foundation Millwork & Stone1st floor>1042026-08-2146
97105 countertops Foundation Millwork & Stone1st floor>1052026-08-2146
98111 countertops Foundation Millwork & Stone1st floor>1112026-08-2146
99112 countertops Foundation Millwork & Stone1st floor>1122026-08-2146
100113 countertops Foundation Millwork & Stone1st floor>1132026-08-2146
109213 Electrical K.E.P. Electric, Inc2nd Floor>2132026-08-3136
110211 Drywall Precision Wall Systems LLC2nd Floor>2112026-08-3136
111214 APPLIANCES GE Appliances2nd Floor>2142026-09-297
112214 CABINET SCRIBEFoundation Millwork & Stone2nd Floor>2142026-09-297
113212 DRYWALLPrecision Wall Systems LLC2nd Floor>2122026-09-297
WGR - Apts I - Bldg D 13 overdue oldest 29 days
#ItemBusiness PartnerLocationDueDays late
14Unit 402 - hvac wire running beneath ceiling. Needs to be moved into ceiling assembly.Romanoff Heating & Cooling2026-09-0729
16All 4th floor units - exterior penetrations need fire caulked Romanoff Heating & Cooling2026-09-0927
17All 4th floor units - line sets need caulked at top/bottom plate.Romanoff Heating & Cooling2026-09-0927
18Unit 419 - kitchen island not square and needs bracingKCL Framing2026-09-0927
23Stairs outside 204 - board uneven at top. Trip hazardKCL Framing2026-09-1818
24Unit 214 shower chasePrecision Wall Systems LLC2026-09-2115
25Unit 320 Tape and mud tub chasePrecision Wall Systems LLC2026-09-2115
26Unit 311 Shower chasePrecision Wall Systems LLC2026-09-2115
27Unit 309 chasePrecision Wall Systems LLC2026-09-2115
28Unit 307 chase Precision Wall Systems LLC2026-09-2115
30Unit 311 - missing shower chase lidPrecision Wall Systems LLC3rd Floor Units>3112026-09-2313
31Unit 309 - missing shower chase lidPrecision Wall Systems LLC3rd Floor Units>3092026-09-2313
33Missing windowsHolmes Lumber2026-09-288
QTR - QT Apts III Bldg E 19 overdue oldest 92 days
#ItemBusiness PartnerLocationDueDays late
29312 Romanoff Rough PunchRomanoff Electric, IncBUILDING E>OVERALL - THIRD FLOOR PLAN>UNIT 312 5 O.C.2026-07-0692
30311 Romanoff Rough PunchRomanoff Electric, IncBUILDING E>OVERALL - THIRD FLOOR PLAN>UNIT 311 5 O.C.2026-07-0692
31310 Romanoff Rough PunchRomanoff Electric, IncBUILDING E>OVERALL - THIRD FLOOR PLAN>UNIT 310 72026-07-0692
32309 Romanoff Rough PunchRomanoff Electric, IncBUILDING E>OVERALL - THIRD FLOOR PLAN>UNIT 309 132026-07-0692
33308 Romanoff Rough PunchRomanoff Electric, IncBUILDING E>OVERALL - THIRD FLOOR PLAN>UNIT 308 42026-07-0692
34307 Romanoff Rough PunchRomanoff Electric, IncBUILDING E>OVERALL - THIRD FLOOR PLAN>UNIT 307 82026-07-0692
35306 Romanoff Rough PunchRomanoff Electric, IncBUILDING E>OVERALL - THIRD FLOOR PLAN>UNIT 306 82026-07-0692
36305 Romanoff Rough PunchRomanoff Electric, IncBUILDING E>OVERALL - THIRD FLOOR PLAN>UNIT 305 32026-07-0692
37304 Romanoff Rough PunchRomanoff Electric, IncBUILDING E>OVERALL - THIRD FLOOR PLAN>UNIT 304 132026-07-0692
38303 Romanoff Rough PunchRomanoff Electric, IncBUILDING E>OVERALL - THIRD FLOOR PLAN>UNIT 303 82026-07-0692
39302 Romanoff Rough PunchRomanoff Electric, IncBUILDING E>OVERALL - THIRD FLOOR PLAN>UNIT 302 5 O.C.2026-07-0692
40301 Romanoff Rough PunchRomanoff Electric, IncBUILDING E>OVERALL - THIRD FLOOR PLAN>UNIT 301 5 O.C.2026-07-0692
41201 Romanoff Rough PunchRomanoff Electric, IncBUILDING E>OVERALL - SECOND FLOOR PLAN>UNIT 201 5 O.C.2026-07-0989
42202 Romanoff Rough PunchRomanoff Electric, IncBUILDING E>OVERALL - SECOND FLOOR PLAN>UNIT 202 5 O.C.2026-07-0989
46206 Romanoff Rough PunchRomanoff Electric, IncBUILDING E>OVERALL - SECOND FLOOR PLAN>UNIT 206 82026-07-0989
54111 Romanoff Rough PunchRomanoff Electric, IncBUILDING E>OVERALL - FIRST FLOOR PLAN>UNIT 111 5B O.C.2026-07-1088
55110 Romanoff Rough PunchRomanoff Electric, IncBUILDING E>OVERALL - FIRST FLOOR PLAN>UNIT 110 7A2026-07-1088
57108 Romanoff Rough PunchRomanoff Electric, IncBUILDING E>OVERALL - FIRST FLOOR PLAN>UNIT 108 4B2026-07-1088
63102 Romanoff Rough PunchRomanoff Electric, IncBUILDING E>OVERALL - FIRST FLOOR PLAN>UNIT 102 5B O.C.2026-07-1088
JPK - JP9 Apts Amenity 12 overdue oldest 774 days
#ItemBusiness PartnerLocationDueDays late
1Plumbing Amenity Space Punch Mike Baumann Plumbing2024-08-23774
2JP9 Shade sail Amenity Space Punch Capital City Awning Co. Inc.2024-08-23774
3Finish Landscaping in JP9 AmenityBlendon Gardens2024-08-23774
4JP9 Amenity Space PunchHolmes Lumber2024-08-23774
5JP9 Flat Black PunchFlat Black, LLC2024-08-23774
6JP9 Punch Amenity punch Supior SteelSuburban Steel Supply Co., LLC2024-08-23774
7JP9 Amenity Punch WolfrumWolfrum Roofing & Exteriors, LLC2024-08-23774
8JP9 Amenity Electrical PunchRomanoff Electric, Inc2024-08-23774
9JP9 Amenity space NNN punchTriple N drywall2024-08-23774
10JP9 Amenity Space Rite Rug PunchRite Rug Co.2024-08-23774
12JP9 Amenity LC&G PunchLC&G Multiservices LLC2024-08-23774
13JP9 Amenity Surface Tech PunchSurface Tech Inc2024-08-23774
QTR - QT Apts III Community Center 10 overdue oldest 312 days
#ItemBusiness PartnerLocationDueDays late
1Exterior Zip PunchKCL FramingExterior2025-11-28312
2Gameroom Precision Drywall PunchPrecision Wall Systems LLCClubhouse>104 Game Rooom2026-06-04124
3Community Room Precision Drywall PunchPrecision Wall Systems LLCClubhouse>103 Community2026-06-04124
4Entry/Cowork Room Precision Drywall PunchPrecision Wall Systems LLCClubhouse>100 Entry/Co-Work2026-06-04124
5Package Room Precision Drywall PunchPrecision Wall Systems LLCClubhouse>110 Package Room2026-06-04124
7Sims-Lohman PunchSims-Lohman, IncClubhouse2026-06-04124
6Rite Rug PunchRite Rug Co.Clubhouse2026-06-05123
8Edgework Creative PunchEdgework CreativeClubhouse2026-06-05123
9Holmes Lumber PunchHolmes LumberClubhouse2026-06-05123
10All Secure PunchAll Secured Security Services LLCClubhouse2026-06-05123
GVX - GVX Apts II Bldg ZZ 6 overdue oldest 60 days
#ItemBusiness PartnerLocationDueDays late
59108 Mech Corridor Contract LumberBuilding>OVERALL - FIRST FLOOR PLAN>MECH. 108A2026-08-0760
86447 - Holmes LumberHolmes Lumber2026-09-0333
87445 - Holmes LumberHolmes Lumber2026-09-0333
94Contract Lumber Interior Trim 2nd Floor West Punch 9-17-26Contract Lumber2026-09-2214
95Sims-Lohman Cabinet 2nd Floor West Punch 9-17-26Sims-Lohman, Inc2026-09-2214
96Contract Lumber Interior Trim 2nd West NPO ItemsContract Lumber2026-09-288
QTR - QT Apts III Maintenance Bldg 8 overdue oldest 196 days
#ItemBusiness PartnerLocationDueDays late
1Maintenance Bldg KCL Frame PunchKCL Framing2026-03-24196
3Maintenance Bldg - JB Hunt Interior Finish PunchWhirlpool Corporation2026-06-18110
4Maintenance Bldg - Sims Lohman Finish PunchSims-Lohman, Inc2026-06-18110
5Maintenance Bldg - TG Interior Finish PunchTG Plumbing & Mechanical, Inc.2026-06-18110
6Maintenance Bldg - Romanoff Interior Finish PunchRomanoff Electric, Inc2026-06-18110
7Maintenance Bldg - Holmes Interior Finish PunchHolmes Lumber2026-06-18110
8Maintenance Bldg - Rite Rug Interior Finish PunchRite Rug Co.2026-06-18110
9Maintenance Bldg - All Secure Interior Finish PunchAll Secured Security Services LLC2026-06-18110
QTR - QT TH&F PB2 2248-2262 8 overdue oldest 901 days
#ItemBusiness PartnerLocationDueDays late
2Tyvek Inspection - 2248-2262 Quarry Trails - 2Thrive Construction2024-04-18901
1Tyvek Inspection - 2248-2262 Quarry Trails - 1Thrive Construction2024-04-19900
3Tyvek Inspection - 2248-2262 Quarry Trails - 3 Thrive Construction2024-04-19900
42260 Appliance install unfinished. Needs hood installedGE Appliances2024-09-27739
52252 Appliance install unfinished. Refrigerator and hood need installed GE Appliances2024-09-27739
62250 Appliance install unfinished. Refrigerator, hood, and dishwasher needs installed. GE Appliances2024-09-27739
72248 Appliance install unfinished. Hood and wall oven needs installedGE Appliances2024-09-27739
82258 Appliance install unfinished. All kitchen appliances need installed. GE Appliances2024-09-27739
QTR - QT TH&F HB4 2867 Kobuk 7 overdue oldest 326 days
#ItemBusiness PartnerLocationDueDays late
101401 APPLIANCESElflein Property Solutions, GE Appliancesavenue.net new WWWV>PLAN FLOOR FOURTH>4012025-11-14326
105202 APPLIANCESElflein Property Solutions, GE Appliancesavenue.net new WWWV>PLAN FLOOR SECOND>2022025-11-16324
106202 PAINTTriple N drywallavenue.net new WWWV>PLAN FLOOR SECOND>2022025-11-16324
108202 ELECTRICALRomanoff Electric Residential LLCavenue.net new WWWV>PLAN FLOOR SECOND>2022025-11-16324
112201 PAINTTriple N drywallavenue.net new WWWV>PLAN FLOOR SECOND>2012025-11-16324
114201 ELECTRICALRomanoff Electric Residential LLCavenue.net new WWWV>PLAN FLOOR SECOND>2012025-11-16324
115201 APPLIANCESElflein Property Solutions, GE Appliancesavenue.net new WWWV>PLAN FLOOR SECOND>2012025-11-16324
WGR - Apts I - Bldg E 2 overdue oldest 18 days
#ItemBusiness PartnerLocationDueDays late
3Unit 203 - missing patio doorway and headerKCL Framing2026-09-1818
2Unit 215 - repair or replace exacore boards. - DAMAGEDKCL Framing2026-10-024
QTR - QT Apts II Bldg P1-P2 5 overdue oldest 500 days
#ItemBusiness PartnerLocationDueDays late
797437 SIMS LOHMANFoundation Millwork & Stone4th Floor Units>4372025-05-24500
843435 GE GE Appliances4th Floor Units>4352025-05-25499
1024437 SIMS LOHMANFoundation Millwork & Stone4th Floor Units>4372025-08-29403
1025419 SIMS LOHMANFoundation Millwork & Stone5th Floor Units>5302025-08-29403
1028537 SIMS LOHMANFoundation Millwork & Stone5th Floor Units>5372025-08-29403
QTR - QT Apts III Bldg H 4 overdue oldest 267 days
#ItemBusiness PartnerLocationDueDays late
152302 Finish Punch JB HuntJB Hunt, Whirlpool CorporationBUILDING H>Third Floor>Unit 302 O.C.2026-01-12267
333104 Finish Punch JB HuntJB Hunt, Whirlpool CorporationBUILDING H>First Floor>Unit 104 13B2026-01-14265
3951st Am exterior punch East side1st AM Construction LLCBUILDING H>Exterior2026-07-0395
404TESTHolmes LumberBUILDING H2026-08-2443
QTR - QT Retail Bldg M Core 4 overdue oldest 580 days
#ItemBusiness PartnerLocationDueDays late
13Leasing-storefront doorsOhio Glass and AluminumA Side (Bada/Leasing)2025-03-05580
16Athletic-Locker roomsRite Rug Co.A Side (Bada/Leasing)2025-03-05580
8Leasing-ceilingRite Rug Co.A Side (Bada/Leasing)2025-03-06579
33Exterior- SidingWolfrum Roofing & Exteriors, LLC2025-03-28557
WGR - Apts I - Bldg C - Comm Ctr 3 overdue oldest 26 days
#ItemBusiness PartnerLocationDueDays late
93Maintenance Room - broken window frame. Top sashHolmes Lumber1st Floor Common Area>Maintenance 0132026-09-1026
132Unit 302 - window grid falling off on 2 windowsHolmes Lumber2026-09-1422
135West side corridor window- broken part of vinyl frame.Holmes Lumber2026-09-1422
QTR - QT Homes ph4 2374 Quarry Trails 1 overdue oldest 8 days
#ItemBusiness PartnerLocationDueDays late
5Win-door issueHolmes Lumber2026-09-288
QTR - QT Homes ph4 2380 Quarry Trails 1 overdue oldest 8 days
#ItemBusiness PartnerLocationDueDays late
4Door leakHolmes Lumber2026-09-288
JPK - JP9 Apts 1 overdue oldest 700 days
#ItemBusiness PartnerLocationDueDays late
655Courtyard Door Punch Holmes LumberHolmes Lumber2024-11-05700
GPK - Grant Pk Apts 5 Bldg B 1 overdue oldest 556 days
#ItemBusiness PartnerLocationDueDays late
50306B Punch Paint/DrywallTriple N drywall2025-03-29556
GVX - 810 Apts Bldg Z 1 overdue oldest 1117 days
#ItemBusiness PartnerLocationDueDays late
6Exterior punch- steal post paintTriple N drywall2023-09-151117
QTR - QT TH&F HB1 2891 Kobuk 1 overdue oldest 1281 days
#ItemBusiness PartnerLocationDueDays late
1NHO - 2891 Kobuk - 402Thrive Construction2023-04-041281

Inspections: lists created, performed, and left unanswered

Procore Inspections (checklist lists) by job. "Dated" lists have an inspection date; "items not inspected" is the share of checklist items never answered Pass, Fail or N/A. A list closed with unanswered items records nothing.

JobListsDatedLast 30dItems not inspectedFailsClosed unansweredTemplates used
GVX - GVX Apts II Bldg ZZCourse of Construction476077%15343ZZ Building Cleanliness (13); ZZ Site Appearance (12); ZZ Site Cleanliness (12); ZZ Safety Checklist (6)
QTR - QT Apts III Bldg HCourse of Construction1414012%24Foundation - Concrete - 100% (2); Claddings - TPO and Scuppers (1); Claddings - Zip Board (1); Foundation - CMU (1)
QTR - QT Apts III Bldg DCourse of Construction99051%01Foundation - CMU (1); Foundation - Excavation and Pre-Construction Meeting (1); Foundation - Footings (1); Foundation - Underground MEPs - 100% (1)
QTR - QT TH&F HB4 2867 KobukCourse of Construction88095%00Foundation - CMU (1); Foundation - Excavation and Pre-Construction Meeting (1); Foundation - Footings (1); Foundation - Poured Walls (1)
QTR - QT Apts III Bldg CCourse of Construction66057%00Foundation - CMU (1); Foundation - Excavation and Pre-Construction Meeting (1); Foundation - Footings (1); Foundation - Underground MEPs - 100% (1)
GVX - GVX Apts II Bldg QCourse of Construction44043%01Foundation - Footings (1); General - Closing and Turnover Window 90-60-and 21-day - Checklist (1); Orientations - Ownership Electrical Walk -100% (1); Orientations - Pre-Drywall Walk (1)
4&5 - 1206 N 4th Apts.Warranty33097%00General - Closing and Turnover Window 90-60-and 21-day - Checklist (2); General - QA - Checklist - 100% (1)
JPK - JP9 AptsWarranty3300%00Tyvek Inspection - JP9 - West Side (2); General - Closing and Turnover Window 90-60-and 21-day - Checklist (1)
MTC - Franklntn Apts Phase CWarranty33088%230General - Closing and Turnover Window 90-60-and 21-day - Checklist (1); General - QA - Checklist - 100% (1); Pool - 100% (1)
QTR - QT Apts II Bldg QWarranty33060%560General - QA - Checklist - 100% (2); General - Closing and Turnover Window 90-60-and 21-day - Checklist (1)
QTR - QT Apts III Community CenterCourse of Construction330100%00Foundation - CMU (1); Foundation - Footings (1); Foundation - Underground MEPs - 100% (1)
QTR - QT TH&F HB3 2842 GunnisonCourse of Construction33063%00Foundation - Excavation and Pre-Construction Meeting (1); Foundation - Footings (1); Orientations - NPO - HOA Turnover (1)
GPK - Grant Pk Apts 5 Bldg AWarranty22074%00General - Closing and Turnover Window 90-60-and 21-day - Checklist (1); General - QA - Checklist - 100% (1)
QTR - QT Apts II Bldg P1-P2Warranty220100%00General - QA - Checklist - 100% (1); Orientations - Ownership Electrical Walk -100% (1)
QTR - QT TH&F PB3 2245-2259 Kings CanyonPre-Construction22099%10General - QA - Checklist - 100% (1); Pre-Construction - For Sale (1)
4&5 - 1206 N 4th GarageWarranty110100%00General - Closing and Turnover Window 90-60-and 21-day - Checklist (1)
GPK - Grant Pk Apts 5 Bldg BWarranty11049%20General - Closing and Turnover Window 90-60-and 21-day - Checklist (1)
GPK - Grant Pk Apts 5 Comm CtrWarranty11070%10Pool - 100% (1)
GVX - 810 Apts Bldg PWarranty110100%00Claddings - Stone (1)
JPK - J67 HB4 270 DickensonWarranty11027%00Orientations - NPO - HOA Turnover (1)
JPK - J67 HB5 260 DickensonCourse of Construction1100%240Pre-Construction - For Sale (1)
JPK - JND Garage Phase 9Warranty1100%220General - Closing and Turnover Window 90-60-and 21-day - Checklist (1)
JPK - JP9 Apts AmenityWarranty1100%70Pool - 100% (1)
QTR - QT Apts III Bldg ACourse of Construction110100%00Foundation - CMU (1)
QTR - QT Apts III Bldg GCourse of Construction11080%00General - Closing and Turnover Window 90-60-and 21-day - Checklist (1)
QTR - QT Apts III Maintenance BldgCourse of Construction11077%00General - Closing and Turnover Window 90-60-and 21-day - Checklist (1)
QTR - QT TH&F HB5 2855 KobukCourse of Construction11082%40Pre-Construction - For Sale (1)
QTR - QT TH&F HB6 2830 GunnisonCourse of Construction110100%00Pre-Construction - For Sale (1)
QTR - QT TH&F PB4 2269-2283 Kings CanyonPre-Construction110100%00Pre-Construction - For Sale (1)
WGR - Apts I - Bldg BPre-Construction11088%00Orientations - Pre-Drywall Walk (1)
WGR - Apts I - Bldg EBidding11021%00Foundation - CMU (1)